Cameco | Freeze Facility HVAC Installation

Freeze Facility HVAC Installation1.jpg
Brine Pumphouse & Central West Piperack Electrical & Instrumentation2.jpg

Client: Cameco, Cigar Lake Mine

Duration of the Work: 106 days

Area of Work: HVAC Installation

Comments: Installed Customer-supplied Air Handling Unit and Makeup Air Unit complete with the required duct work for supply, exhaust, outdoor air and return air; complete with fire dampers, grills and registers. Supplied and installed burner B-Vent and supports. Supplied and installed four (4) weather hoods on exterior of building.