Cameco | Brine Pumphouse Mechanical & Piping

SPC Island Falls Ventilation Upgrades1.jpg
SPC Island Falls Ventilation Upgrades2.jpg
Brine Pumphouse Mechanical & Piping3.png

Client: Cameco, Cigar Lake Mine

Duration of the Work: 183 days

Area of Work: Mechanical equipment installation, Piping Installation (grooved & welded) work for brine pumping system.

Comments: This work was executed during the winter months in parallel with multiple other contracts including the Brine Pumphouse & Central West Piperack E&I. In order to successfully execute these contracts, Tron carefully scheduled and coordinated multiple trades working in several congested work faces. Tron’s Project teams worked closely internally as well as with the Clients Representative to ensure that there was minimal disruptions.